Construction Notices

Print

Construction notices are updated weekly to provide an in-depth look at any Department of Public Services projects that may impact traffic or parking in the City of Newport.

As always, we appreciate everyone’s cooperation while the State and City work together to improve the safety and aesthetics of our transportation infrastructure network.

Cliff Walk Repairs 2016-17

The City of Newport’s Cliff Walk contractor, New England Building and Bridge (NEBB) will begin work on Monday, March 28, 2017, on the Cliff Walk just north of Ruggles Avenue. The Cliff Walk will be closed 24-hours a day just north of Ruggles Avenue starting Tuesday, March 28, 2017, at 7:00 am for approximately four (4) weeks.  We anticipate approximately 250 feet of path immediately north of Ruggles Avenue being closed as the contractor works in this area to install a new concrete walking surface, rip-rap, concrete retaining wall, and drainage improvements.  Pedestrians will be detoured around the closed area utilizing Shepard Avenue, Ochre Point Avenue, and Ruggles Avenue sidewalks. Access to the Cliff Walk south of Ruggles Avenue will remain open and may be accessed directly from Ruggles Avenue.  The Cliff Walk will be open north of Shepard Avenue up to the closed section of the path approximately 250 feet north of Ruggles Avenue.  

Funding for the project comes from a National Park Service Hurricane Sandy Relief Grant, administered by the Rhode Island Historical Preservation & Heritage Commission, Rhode Island Department of Transportation, and the City of Newport. 

We thank you all for your patience while construction continues on the Cliff Walk. 

Contractor: New England Building & Bridge Company, Greenville, RI
Status: Work resumes Monday, March 27, 2017
Progress: 74%
Contract Amount: $936,248.37 approved docket April 25, 2016. (includes $580,938.00 RIHPHC Grant funding)
Contract Completion: June 30, 2017
Locations: Cliff Walk: Narragansett Avenue to Webster Street, north of Ruggles Avenue, south of Ruggles Avenue, and at end of Narragansett Avenue.

Contact Information:

Department of Public Services
William Boardman, PE, City Engineer
Phone: (401) 845-5842
Email: WBoardman@CityofNewport.com

Roadway Improvement Program 2015-16
Narragansett Improvement Co. (NICO) is working to restore city roadways and sidewalks throughout the city.

Contractor: Narragansett Improvement Company
Status: Winter Shut-down, will resume in spring 2017.
Progress: 99%
Contract Amount: $3,461,277.09 approved docket April 25, 2016. (includes $30,690.00 CDBG funding)
Contract Completion: November 20, 2016

Current road work:

Road work is substantially complete.

Parking may be restricted from 7 AM to 4 PM Monday through Friday. Roads may be closed during working hours, but will generally remain open to local traffic.

Contact Information:

Narragansett Improvement Company
Chris Beauchamp, Superintendent
Phone: (401) 996-9484

Department of Public Services
William Boardman, PE, City Engineer
Phone: (401) 845-5842
Email: WBoardman@CityofNewport.com

 

Pavement Marking Program 2016-17
Safety Marking Inc. will begin work to repaint pavement markings throughout the city.

Contractor: Safety Marking Inc.
Start: Winter Shut-down, will resume in spring 2017.
Location: City-wide on roadways with existing pavement markings.

Progress: 60%
Contract Amount: $75,028.30 approved docket September 15, 2016.
Contract Completion: June 30, 2017

Contact Information:

Department of Public Services
William Boardman, City Engineer
Phone: (401) 845-5842
Email: WBoardman@CityofNewport.com

 

Sidewalk Improvement Program 2016-17
LAL Construction Company, Inc. will begin work to restore city sidewalks in select locations throughout the city.

Contractor: LAL Construction Company, Inc.
Status: Winter Shut-down, will resume in spring 2017.
Progress: 25%
Contract Amount: $452,583.18 approved docket July 22, 2016.
Contract Completion: June 30, 2017

Contact Information:

LAL Construction Company, Inc.
Mike Louro, Superintendent
Phone: (508)676-3962 ext.18 

Department of Public Services
William Boardman, City Engineer
Phone: (401) 845-5842
Email: WBoardman@CityofNewport.com


Broadway Streetscape Improvement Project
Cardi Corporation is working to restore the Broadway corridor as part of this complete-streets project.

Start: April 2017
Location: Broadway (Farewell Street to Cranston Avenue)

Marlborough Street Urban Bioswale (Rain Garden) Construction.

RIDOT Project Page

Contact Information:
Rhode Island Department of Transportation (RIDOT)
Phone: (401) 222-2450

Email: dot.customerservice@dot.ri.gov

 

 

 

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer